WARNING - By their nature, text files cannot include scanned images and tables. 
The process of converting documents to text only, can cause formatting changes 
and misinterpretation of the contents can sometimes result. Wherever possible 
you should refer to the pdf version of this document.



Page 1


CAIRNGORMS NATIONAL PARK AUTHORITY 
Paper 8 21/01/11 

CAIRNGORMS NATIONAL PARK AUTHORITY 


FOR INFORMATION 


Title: 
Corporate Plan Monitoring 

Prepared by: David Cameron, Corporate Services Director 

Purpose 

To present the results of the latest update on progress against organisational objectives on 
the basis of the corporate plan monitoring framework. 

To present an update on the Management Team’s initial overview of the Authority’s 
capacity to continue to deliver the Corporate Plan Outcomes in 2011/12 in light of draft 
budget allocations announced in November 2010 and associated changes in resource levels. 

Recommendations 

a) 
The Board is asked to note the report, and to raise any questions on the update 
provided. 

Executive Summary 

Update on Progress toward Delivery of Corporate Plan Achievements 

1. 
The Board agreed the extension of the Corporate Plan, with some modifications, at 
its meeting of 3 September 2010. (See 
http://www.cairngorms.co.uk/resource/docs/boardpapers/03092010/CNPA.Paper.37 
62.Board.Paper.1.Corp.Pl.pdf ). 

2. 
The latest update of performance against these revised corporate objectives and 
associated milestones is presented at Annex 1 to this paper. The updates reflect 
progress made to the end of November 2010. 
3. 
There are no exceptions to report to the Board at this point in terms of specific 
outcomes which are assessed to be at significant risk of non-delivery. None of the 48 
achievements are currently assessed as red, which would indicate significant risk of 
not being delivered within the Corporate Plan period. 
4. 
All Corporate Plan achievements are assessed either as “green” – and should be 
achieved with existing levels of forecast resource and time allocation – or “amber”, 
where progress against the outcome has fallen behind expectation to date. While 
the achievements rated amber are still assessed as deliverable by March 2012, there 
is some heightened level of risk around their not being delivered or timetables not 
being met. Currently 5 of the 48 Corporate Plan outcomes are assessed as amber, 
as set out in Annex 1. 

Page 2



5. 
Nor are there exceptions to report at this point in terms of any overall priorities for 
action which are at risk through a preponderance of achievements currently 
highlighted as amber and therefore at some heightened risk of non- or partial 
delivery by the end of the current Corporate Plan period. 
Review of Corporate Plan Delivery into 2011/12 

6. 
The requirement to undertake a further review of the capacity to deliver corporate 
objectives in light of the Comprehensive Spending Review announcements was 
highlighted to the Board in September. The Management Team has now undertaken 
an initial review of the capacity to deliver the modified Corporate Plan in light of the 
draft grant allocations announced by the Scottish Government in November 2010 
and staff resource availability following on from the recent voluntary severance 
scheme. 
7. 
The modifications to the Corporate Plan were made with the potential for up to 
10% reductions in grant in aid from Scottish Government for 2011/12 in mind. The 
current draft budget put forward by the Scottish Government indicates an actual 
reduction in grant in aid of 4.4% for 2011/12. Our longer term financial planning 
continues to be driven by the potential for further budget amendments in 2011/12 
following elections in May, together with ongoing expectation of budget reductions 
into future years. 
8. 
A voluntary severance scheme implemented to help manage the Authority’s forward 
staffing commitments in the context of these forward financial drivers has resulted in 
5 staff leaving the Authority in late 2010. This represents a reduction in staff 
resources of almost 10%. 
9. 
In light of the reduction in financial and staff resources, the Management Team’s 
initial review of the Corporate Plan indicates that, while the amendments in 
September were made in expectation of resource reductions of this general 
magnitude, some further adjustments are required. These adjustments are set out in 
the following table, with reference numbers relating to the achievement / outcome 
reference number as set out in Annex 1: 
Outcome 
Ref 
Change Required Rationale / Comment 
7 2012 Milestone change: Positive 
reports on delivery of Woodfuel 
Action Plan and Spey Catchment 
Project [removes proposal for new 
pilot project to be launched in 2012]. 
Already implemented some shift in 
resource use through cessation of Land 
Management Support project. No new 
projects to be initiated on 2011/12 – 
concentrate in year on achieving 
outcome through delivery of existing 
projects. 
8 Revised achievement: positive report 
on implementation of the deer 
framework 
Better reflects on focus of CNPA’s 
effort, rather than current outcome 
focus on habitat that will be delivered 
by others. 
11 2012 Milestone change: 70% of 
network is fit for purpose [reduction 
from original milestone of 90%]. 
Milestone of 70% for 2011 will not be 
achieved. Resources / capacity not 
sufficient to catch up on backlog and 
also undertake new work to achieve 

Page 3



Outcome 
Ref 
Change Required Rationale / Comment 
current 90% target by 2012. 
12 2012 Milestone change: becomes 
planning permission granted and paths 
agreements orders in place. 
Legal delays in progress over 2010 
cannot be recovered for construction 
work to commence by March 2012. 
12 Revise Corporate Plan outcome: All 
regulatory and statutory requirements 
are in place for construction work on 
Speyside Way extension to 
commence. [Removes construction 
work has commenced on Speyside 
Way.] 
Better fit to split of responsibility 
between CNPA – legal process re path 
orders / inquiries and planning, and 
COAT – funding package, bidding, and 
contracting works. 
23 Outcome will not be progressed 
further in its own right. 
Insufficient resources for CNPA to 
progress research and proactive 
promotion of sites for affordable 
housing. Will focus delivery of these 
aspects within outcome 24 – through 
rural housing enabler projects. 
25 2012 milestone – replace promotion 
of at least one new demonstration 
event with establishing a ‘design 
award’. 
Focus on existing planned activities. 
36 Outcome will not be progressed 
further in its own right. 
Focus of resource on development of 
NPP2 and future stakeholder 
engagement, rather than reviewing 
extent to which partners are currently 
reflecting work in NP within their 
corporate plans / annual reports. 
40 2012 Milestone change: main issues 
identified to inform LDP as milestone 
[to replace preparation of proposed 
plan]. 
Refinement of milestone – timetable 
such that we will not be in a position 
to prepare LDP by March 2012. 
44 2012 Milestone change: focus on joint 
NPA corporate services delivery 
[removes reference to Best Value 
Action Plan]. 
Work on Best Value Action Plan 
should be completed by end March 
2011 and focuses work on joint 
Corporate Services development 
between NPAs over the coming year. 
47 2012 Milestone change: add in target 
of delivering 3% efficiency saving per 
Nov Budget report. 
Additional milestone to outturn target, 
reflecting efficiency targets set out in 
Scottish Government budget 
proposals. 

10. 
Overall, therefore, it is proposed that work will cease on 2 of the 48 Corporate Plan 
achievements, with adjustments made to the focus of 2 other achievements. 
Corporate Priorities and Resource Allocations – Next Steps 

11. 
The Management Team review is presented for information at this stage, to give 
assurance to Board members that capacity issues raised by reductions in the 
Authority’s resource are being addressed. 

Page 4



12. 
Work is ongoing on potential staff and financial resource allocations for 2011/12 and 
it is intended that initial draft budget proposals will be presented to the Finance 
Committee for consideration at its meeting in February 2011. 
13. 
Budget proposals for 2011/12 will then be presented to the Board meeting in March 
2011, at which time there will be opportunity for the Board to consider in more 
detail the overall prioritisation of activity for the final year of the current 2008 to 
2012 Corporate Plan, and consequent budget allocations. 
“Balanced Scorecard” Key Performance Indicators 

14. 
The latest review of the Authority’s performance against a range of Key 
Performance Indicators (KPIs) is summarised in the balanced scorecard in Annex 2. 
The assessment now presented represents performance to end November 2010. 
15. 
In general, analysis of performance against KPIs reflects a very strong performance 
by the Authority on these adopted key indicators. 
Financial Management 

16. 
There are no specific exceptions to highlight on financial management indicators at 
this time. Performance against 2010/11 budget expectations is broadly on target, 
while forward commitments are within control totals and monitored regularly by 
Finance Committee. 
Human Resource (HR) Management 

17. 
The only slight area of concern highlighted by key performance indicators related to 
the Authority’s staff is around turnover and potential disruption caused. 
18. 
Other than this area, all HR indicators are in line with target measures. 
Governance and Risk Management 

19. 
The level of complaints received by the Authority has seen an upturn over the last 4 
months and this area is now highlighted as at some risk. Many of the complaints 
received are linked in some way to the Authority’s planning activities. 
20. 
Other governance and risk management indicators remain at target levels. 
Corporate Plan Delivery and Contribution to Scottish Government Outcomes 

21. 
At this point in the year, I have not sought to update all KPIs relating to Corporate 
Plan delivery. This will be undertaken for the next monitoring update to Board and 
will present a year end position for 2010/11. 
22. 
One exception to this relates to the KPI on reducing emissions from vehicle based 
business travel, for which we collect data quarterly. With three quarters of the year 
gone, available data suggests that the Authority will achieve a further substantial 
reduction in its carbon emissions from vehicle travel in 2011/12. 
DAVID CAMERON 
11 January 2011 

davidcameron@cairngorms.co.uk